Slider

PROJECT STATUS

December 2020


Work Accomplished :
  • Raft foundation complete.
  • RCC work for three level basement complete.
  • Plinth work complete.
  • Total RCC work complete.
  • Brick work completed up to 13th floor.
  • Internal plaster work completed up to 13th floor.
  • External plaster work completed up to 9th floor.
  • Kitchen platform and dado tiling work completed up to 11th floor.
  • Plumbing work completed up to the 11th floor.
  • Gypsum work completed up to 9th floor.
  • Electrical concealed work completed from 11th floor.
  • Total plumbing concealed work & dado tiling work is completed up to 9th floor.
  • Waterproofing work completed up to the 11th floor.
The work has been carried out as per above said approval but with minor modifications of approvable nature.

Architect Certificate

February 2020


Work Accomplished :
  • Slab Casting of 12th Slab
  • Work in Progress for 13th Slab
  • Block Work at 10th Floor
  • Internal Plaster Work upto 8th Floor
  • External Plaster Work upto 8th Floor in Progress
  • Window Framing Work upto 8th Floor
  • Gypsum Work upto 4th Floor
  • Bathroom Tiling Work upto 4th Floor
  • Concealed Electrical Work upto 9th Floor
  • Concealed Plumbing Work upto 7th Floor

Architect Certificate
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019

December 2019


Work Accomplished :
  • Slab Casting Completed of 9th Slab
  • Work in Progress for 10th Slab
  • Block Work upto 6th Floor
  • Plaster Work upto 5th Floor
  • Window Framing Work upto 5th Floor

Architect Certificate
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019
Construction Status of the Project as of December, 2019

September 2019


Work Accomplished :
  • Reinforcement of Slab for 7th Floor, Flat No. 1 & 2, B Wing
  • Shuttering of Bottom Beam for 7th Floor, B Wing
  • Shuttering & Casting of Columns Above 5th Floor, B Wing
  • Block Work at Flat No. 301 & 302, A Wing
  • Plaster Work at Flat No. 202, A Wing
  • Window Framing Work at Flat No. 101, A Wing

Architect Certificate
Construction Status of the Project as of September, 2019
Construction Status of the Project as of September, 2019
Construction Status of the Project as of September, 2019
Construction Status of the Project as of September, 2019

August 2019


Work Accomplished :
  • Shuttering of Slab for 6th Floor, Flat No. 1 & 2, B Wing
  • Shuttering & Casting of Columns Above 5th Floor, B Wing
  • Block Work Repairing at 1st Floor of A & B Wings
  • Reinforcement of Beam for 6th Floor Slab, Flat No. 3 & 4, A Wing

Architect Certificate
Construction Status of the Project as of August, 2019
Construction Status of the Project as of August, 2019
Construction Status of the Project as of August, 2019

June 2019


Work Accomplished :
  • Shuttering of Slab for 4th Floor, Flat No. 1 & 2, A Wing
  • Shuttering & Casting of Columns Above 3rd Floor, B Wing
  • Reinforcement of Columns Above 3rd Floor, B Wing

Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019
Construction Status of the Project as of June, 2019

May 2019


Construction Status of the Project as of May, 2019
Construction Status of the Project as of May, 2019
Construction Status of the Project as of May, 2019
Construction Status of the Project as of May, 2019
Construction Status of the Project as of May, 2019

March 2019


Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019
Construction Status of the Project as of March, 2019