PROJECT STATUS
December 2020
Work Accomplished :
- Raft foundation complete.
- RCC work for three level basement complete.
- Plinth work complete.
- Total RCC work complete.
- Brick work completed up to 13th floor.
- Internal plaster work completed up to 13th floor.
- External plaster work completed up to 9th floor.
- Kitchen platform and dado tiling work completed up to 11th floor.
- Plumbing work completed up to the 11th floor.
- Gypsum work completed up to 9th floor.
- Electrical concealed work completed from 11th floor.
- Total plumbing concealed work & dado tiling work is completed up to 9th floor.
- Waterproofing work completed up to the 11th floor.

February 2020
Work Accomplished :
- Slab Casting of 12th Slab
- Work in Progress for 13th Slab
- Block Work at 10th Floor
- Internal Plaster Work upto 8th Floor
- External Plaster Work upto 8th Floor in Progress
- Window Framing Work upto 8th Floor
- Gypsum Work upto 4th Floor
- Bathroom Tiling Work upto 4th Floor
- Concealed Electrical Work upto 9th Floor
- Concealed Plumbing Work upto 7th Floor





December 2019
Work Accomplished :
- Slab Casting Completed of 9th Slab
- Work in Progress for 10th Slab
- Block Work upto 6th Floor
- Plaster Work upto 5th Floor
- Window Framing Work upto 5th Floor







September 2019
Work Accomplished :
- Reinforcement of Slab for 7th Floor, Flat No. 1 & 2, B Wing
- Shuttering of Bottom Beam for 7th Floor, B Wing
- Shuttering & Casting of Columns Above 5th Floor, B Wing
- Block Work at Flat No. 301 & 302, A Wing
- Plaster Work at Flat No. 202, A Wing
- Window Framing Work at Flat No. 101, A Wing





August 2019
Work Accomplished :
- Shuttering of Slab for 6th Floor, Flat No. 1 & 2, B Wing
- Shuttering & Casting of Columns Above 5th Floor, B Wing
- Block Work Repairing at 1st Floor of A & B Wings
- Reinforcement of Beam for 6th Floor Slab, Flat No. 3 & 4, A Wing




June 2019
Work Accomplished :
- Shuttering of Slab for 4th Floor, Flat No. 1 & 2, A Wing
- Shuttering & Casting of Columns Above 3rd Floor, B Wing
- Reinforcement of Columns Above 3rd Floor, B Wing








May 2019





March 2019